Papa Terra Field CP retrofit – Brava Energia & Imenco Corrosion Technology

image

Brava’s statement:

‘Imenco delivered their retrofit Piranha® Anode Clamp solution to us, and they helped us install it on our Papa Terra field in Q2 2025. We are very satisfied with the quality of both aspects delivered’, says Rafael Terzi and Priscilla Borges, Brava Energia Subsea Engineers.

Challenge:

At the Papa Terra Field offshore Brazil, Brava Energia identified critical cathodic protection (CP) deficiencies during routine subsea inspections. Measurements revealed that Xmas trees, RxF connectors, and choke valves had fallen below protective CP levels due to depleted anodes, exposing this critical production equipment to corrosion in the field’s challenging deepwater environment.

Solution:

Imenco Corrosion Technology engineered a customized retrofit solution featuring:

·

Benefits:

·

Result:

The team successfully:

image
Piranha® Clamps (red circles) successfully installed on Xmas Tree, demonstrating its robust gripping capability for critical subsea infrastructure.

image
Piranha® Clamps securely installed on Umbilical Connector

Key Success Factors:

1. Collaborative Execution

image

Photo 1: Imenco technician conducting precision testing and calibration of Imenco Clamp Installation Tool (ICIT) to ensure correct installation torque would be applied.

Photo 2: ICIT interface

image
To enable fast installation and minimize operational downtime, ROV team efficiently deployed six Piranha® Clamps on a single basket – ensuring secure, time-saving performance in demanding subsea conditions.

2. Technical Superiority

Let us know if there is anything we can do
to help you!

Consent(Required)
This field is for validation purposes and should be left unchanged.